October 30, 2017
Kyushu Electric Power Company Inc.
Changes in Application of Pre-Operation Inspection regarding
Genkai Nuclear Power Station Unit No.3

 Today, we carried out the procedures pertaining to changes in contents to the Nuclear Regulatory Authority (NRA) based on the Reactor Regulation Act, etc. This is a result of reviewing the inspection process regarding application of pre-operation inspection of Genkai Nuclear Power Station Unit No.3, which we submitted to NRA on August 28, 2017, considering the progress of inspection.

 We will respond sincerely and politely to the pre-operation inspection by the NRA and making best effort to assure the safety check for the restart of our nuclear power station as well as communicate with the community.

[Changes in Application of Pre-Operation Inspection]

Schedule of the inspection
  Before After
Inspection No.1 From September 11, 2017
To October 2017
From September 11, 2017
To November 2017
Inspection No.3 From September 2017
To November 2017
From September 14, 2017
To November 2017

*No changes in the inspection process regarding Inspection No.2, 4 and 5.