Regarding Genkai Nuclear Power Station Unit No.4, we restarted generating electricity on June 19, and plan to undergo the Inspection No.5, which is the final pre-operation inspection to confirm comprehensive performance, on July 18 and 19.
Based on the Reactor Regulation Act, etc., we took the change procedure of the application for pre-operation inspection submitted to the Nuclear Regulatory Authority(NRA) today.
We will continue to make sincerely an all-out effort to deal with the NRA's inspections, and carry out restart process of commercial operation carefully.
【Changes of Application of Pre-Operation Inspection of Genkai Unit No.4】
[Schedule of the inspection]
|
|
Before
|
After
|
Inspection No.4
|
From May 2018
To June 2018
|
From May 30, 2018
To June 1, 2018
|
Inspection No.5
|
July 2018
|
From July 18, 2018
To July 19, 2018
|
[Inspection contents]
Inspection No.4:
Check the functions and performance when the nuclear power reactor is ready for startup.
Inspection No.5:
Check the performance of the nuclear power station comprehensively when the plant is operating at constant rated thermal power output.
|
|