February 18, 2019
Kyushu Electric Power Co., Inc.
Approval of Construction Planning regarding Newly installed facilities of Specific Safety Facilities for Sendai Nuclear Power Station Unit No.1

 We have applied separately in three divisions for approval of construction planning regarding Specific Safety Facilities (SSFs) of Sendai nuclear power station unit No.1.
 Today, we received the approval regarding "Newly installed facilities" which is the third division, from Nuclear Regulatory Authority (NRA).

 We will continue to make an effort to deal with the NRA's inspections respectfully and sincerely, for improving safety and reliability of nuclear power stations.

(Reference)

 Applications for approval of construction planning were submitted separately as below with a view to install SSFs within the time required by laws.

1. Facilities installed in a reactor subsidiary building
2. Newly installed buildings
3. Newly installed facilities

○Status of application regarding SSFs of Sendai nuclear power station unit No.1

Division Facilities Day of Application and Approval
First Facilities installed in a reactor subsidiary building (Application)
 May 24, 2017
(Approval)
 May 15, 2018
Second Newly installed buildings (Application)
 August 8, 2017
(Approval)
 July 26, 2018
Third Newly installed facilities (Application)
 March 9, 2018
(Revision)
 October 23, 2018
 November 19, 2018
 December 20, 2018
(Approval)
 February 18, 2019(Today)