March 20, 2018 Kyushu Electric Power Company Inc. |
Rejection of the Temporary Injunction against Restart of Genkai Nuclear Power Station Units No.3 and 4 (Kyushu Electric Power Prevails in Court) |
The lawsuit was filed on January 27, 2017, seeking to prohibit the restart of Genkai Nuclear Power Station Units No. 3 and 4. Saga District Court rejected the temporary injunction which the petitioner filed, and said that there was no specific risk of severe accidents at Genkai Nuclear Power Station. We will continue our voluntary initiatives to further enhance safety and reliability and will make every effort to ensure the safety of Genkai Nuclear Power Station. |