Today, we submitted the change notification of electricity supply plan* of power generation and retail sectors to Organization for Cross-regional Coordination of Transmission Operators (OCCTO) as a result of restart of Genkai nuclear power station unit No.3 and 4.
We announce that we revised the power plant discontinuation and planned suspension plan in this notification as follows.
* = |
Plan regarding the next ten years forecasts for electricity demand and power plant development and discontinuation etc., which is notified to the Ministry of Economy, Trade and Industry via OCCTO in accordance with the Electricity Business Act. |
[Discontinuation]
Type |
Power plant & unit |
Output |
Schedule |
Thermal power
(Heavy crude) |
Ainoura unit 1, 2 |
875,000 kW |
April 2019
【FY2018】 |
Buzen unit 1 |
500,000 kW |
FY2019
【FY2020~Planned Suspension】 |
[Planned Suspension]
Type |
Power plant & unit |
Output |
Schedule |
Thermal power
(Heavy crude) |
Buzen unit 2 |
500,000 kW |
FY2018~
【FY2020~】 |
Sendai unit 1, 2 |
1,000,000 kW |
FY2018~
【 - 】 |
Thermal power
(LNG) |
Shin-Kokura unit 4 |
600,000 kW |
FY2020~
【 - 】 |
Note: 【 】indicates last fiscal year plan.
|