August 10, 2015

Kyushu Electric Power Company Inc.
The Schedule of Startup and Restart Generating Electricity of Sendai Nuclear Power Unit No.1

 We hereby announce that as of today, Sendai Nuclear Power Unit No.1 (Pressurized Water Reactor, 890MW output), which is under the 21st periodic inspection, is expected to start up on August 11, and restart generating electricity on August 14.

 After restarting generating electricity, we will conduct the adjustment operation as increasing output gradually. Accordingly, the plant is expected to undergo the verifying the overall plant performance and return to the normal operation at the beginning of September.

 We will continue to make sincerely an all-out effort to deal with the Nuclear Regulation Authority's inspections, and carry out carefully remaining process, putting utmost priority to safety.