September 14, 2017 Kyushu Electric Power Company Inc. |
Construction Planning Permission of Genkai Nuclear Power Station No.4 and Permission for Change in Safety Regulations of Genkai Nuclear Power Station |
Today, we hereby announce that we received the construction planning permission(detailed design) of Genkai nuclear power station No.4 and the permission for change in safety regulations (operational management, system) of Genkai Nuclear Power Station from Nuclear Regulatory Authority (NRA). We applied for them on July 12th 2013 in order to be reviewed regarding conformance to the new regulatory requirements. We will apply for the pre-operation inspection of Genkai No.4 to confirm that the safety measure equipment at the power station is in accordance with the permitted construction planning. We will continue to diligently and carefully handle to the NRA's review, and make efforts to communicate with the community. (Status of Genkai regarding conformance to the new regulatory requirements)
|