June 25, 2018
Kyushu Electric Power Co., Inc.
Reapplication of Changes in Application of Pre-Operation Inspection regarding Genkai Nuclear Power Station Unit No.4

 Regarding Genkai Nuclear Power Station Unit No.4, we restarted generating electricity on June 19, and plan to undergo the Inspection No.5, which is the final pre-operation inspection to confirm comprehensive performance, on July 18 and 19.
 Based on the Reactor Regulation Act, etc., we took the change procedure of the application for pre-operation inspection submitted to the Nuclear Regulatory Authority(NRA) today.

 We will continue to make sincerely an all-out effort to deal with the NRA's inspections, and carry out restart process of commercial operation carefully.

【Changes of Application of Pre-Operation Inspection of Genkai Unit No.4】

[Schedule of the inspection]
  Before After
Inspection No.4 From May 2018
To  June 2018
From May 30, 2018
To  June 1, 2018
Inspection No.5 July 2018 From July 18, 2018
To  July 19, 2018

[Inspection contents]

Inspection No.4:
 Check the functions and performance when the nuclear power reactor is ready for startup.

Inspection No.5:
 Check the performance of the nuclear power station comprehensively when the plant is operating at constant rated thermal power output.