(Information)Application for approval of construction planning regarding "newly installed buildings" of Specific Safety Facilities for Genkai nuclear power station units No.3 and 4

 As for Specific Safety Facilities(SSFs) of Genkai Nuclear Power Station No.3 and 4, of which we received the permission for a change in reactor installation on April 3, 2019, we divide procedures for applications for approval of construction planning into three: "facilities installed in a reactor subsidiary building", "newly installed buildings", and "newly installed facilities".
 Today, we submitted the application regarding "newly installed buildings" to Nuclear Regulatory Authority (NRA).

 We divide the applications for efficient constructions of SSFs. And we are going to submit the remaining applications of "newly installed facilities", as soon as we get prepared.

 We will make an effort to deal with the NRA's inspections respectfully and sincerely, as well as to improve safety and reliability of nuclear power stations.

(Reference)

 ○Application status regarding the Specific Safety Facilities for Genkai Nuclear Power Station No.3 and 4

  Genkai No.3 Genkai No.4
Facilities installed in a reactor subsidiary building (Application)May 16, 2019 (Application)June 18, 2019
Newly installed buildings (Application)September 19, 2019(today) (Application)September 19, 2019(today)