Please note that our fiscal year differs from the calendar year. Our fiscal year starts April 1 and ends March 31.

FY2020

FY2019

31-03-2020 Investor FAQ about FY2019 (as of March 31, 2020)
24-03-2020 Kyushu Electric Power Co., Inc. has been commissioned by JICA to undertake the Project on Electricity Sector Master Plan Study for Development of Renewable Energy for the Republic of Cuba -Utilization of Kyuden Group knowledge to promote the introduction of renewable energy in Cuba-
31-01-2020 Revision of Financial Results Forecast for FY2019
31-01-2020 Financial Results for 3rd Quarter of FY2019
08-01-2020 Participation in Philippine Microgrid Project of PowerSource Group -our 1st overseas off-grid electrification project for remote island-
25-12-2019 Kyuden signs Agreement with NYK and MOL for the World's First LNG-fueled Large Coal Carrier -Reduction of GHG Emission by implementing LNG Fuel-
20-12-2019 Kyushu Electric Power Company Starts Commercial Operation of Matsuura Power Station Unit 2 -Largest in scale in Japan as a single unit with 1GW of output-
19-12-2019 Kyuden International Corporation opens a new branch office in Tokyo -Strengthening information gathering and expanding business areas and scope-
19-12-2019 Share Purchase Agreement for Taweelah B Independent Water & Power Producer Project -our 1st IWPP project in the UAE (Equity ownership of 120MW)-
17-12-2019 Please beware of fake job offers from scammers posing as a company officer
11-12-2019 Issuance of Kyushu Electric Power Company's 487th Bonds
06-12-2019 Issuance of Kyushu Electric Power Company's 486th Bonds
03-12-2019 Participation in a Joint Development Project in Atlanta, Georgia, U.S.
29-11-2019 Participation in Westmoreland Gas-Fired Power Project -our 4th power generation project in the USA (Equity ownership of 118MW)-
28-11-2019 (Information)Approval of construction planning of Specific Safety Facilities for Genkai Nuclear Power Station Units No.3 and 4 -Approval of "facilities installed in a reactor subsidiary building"-
22-11-2019 Issuance of Kyushu Electric Power Company's 484th and 485th Bonds
31-10-2019 Revision of Financial Results and Dividends Forecast for FY2019
31-10-2019 Financial Results for 2nd Quarter of FY2019
31-10-2019 Notice Regarding Adjustment of Conversion Price for Zero Coupon Convertible Bonds due 2020 and 2022
03-10-2019 Changes to the Sendai Nuclear Power Station Units 1 and 2 Operation Plans
01-10-2019 Kyuden International Corporation establishes representative office in Thailand -KIC's first overseas office in Asia-
25-09-2019 Fukuoka High Court Rejects the Petition to Halt Genkai Nuclear Power Station Units 3 and 4 (Filed in FY2017) -Ruling in favor of Kyushu Electric Power-
19-09-2019 (Information)Application for approval of construction planning regarding "newly installed buildings" of Specific Safety Facilities for Genkai nuclear power station units No.3 and 4
02-09-2019 Tokyo Gas and Kyuden Established Chiba Sodegaura Power Co.,Ltd.
28-08-2019 Issuance of Kyushu Electric Power Company's 482nd and 483rd Bonds
31-07-2019 Information regarding publishing of Kyuden Group Annual Report 2019
31-07-2019 Financial Results for 1st Quarter of FY2019
19-07-2019 Issuance of Kyushu Electric Power Company's 480th and 481st Bonds
10-07-2019 Court Decision to Dismiss the Appeal for the Temporary Injunction (filed in FY2011) against Genkai Nuclear Power Station Units 3 and 4 -Ruling in favor of Kyushu Electric Power-
03-07-2019 Supporting the Recommendations Issued by the Task Force on Climate-related Financial Disclosures(TCFD) -Contributing to the development of a sustainable society through climate-related financial disclosures-
28-06-2019 Notice Regarding Reset of Conversion Price for Zero Coupon Convertible Bonds due 2020
28-06-2019 UPdated Procurement Plan for FY2019
26-06-2019 Notice Regarding Adjustment of Conversion Price for Zero Coupon Convertible Bonds due 2020 and 2022
19-06-2019 (Information)Application for approval of construction planning regrading "facilities installed in a reactor subsidiary building" of Specific Safety Facilities for Genkai nuclear power station unit No.4
17-06-2019 Updated Presentation Materials
07-06-2019 Formulation of the "Kyuden Group Management Vision 2030" -For the sustainable development of Kyushu and to grow together with the region and society-
07-06-2019 Issuance of Kyushu Electric Power Company's 479th Bonds
07-06-2019 Issuance of Kyushu Electric Power Company's 478th Bonds
07-06-2019 Birdsboro Gas-Fired Power Plant in Operation -Kyuden's First U.S. Power Generation Project Commercially Starts-
31-05-2019 Start of power generation of Matsuura Power Station Unit 2 -Start of power generation with the trial run starting on June 1, 2019-
17-05-2019 Issuance of Kyushu Electric Power Company's 476th and 477th Bonds
17-05-2019 Updated Financial Results
16-05-2019 (Information)Application for approval of construction planning regrading "facilities installed in a reactor subsidiary building" of Specific Safety Facilities for Genkai nuclear power station unit No.3
15-05-2019 First LNG Bunkering Operation in the Setouchi and Kyushu Areas of Western Japan
14-05-2019 Indirect Shares Acquisition of EGCO in Thailand -Contributing the electricity business together with the high-growth companies in Asia-
26-04-2019 Financial Results for FY2018
25-04-2019 Total Electricity Sales Volume in FY2018
22-04-2019 Revision of Class A preferred share
16-04-2019 Revision of Forecasts of Financial Results for FY2018
12-04-2019 (Information)Approval of Construction Planning regarding Newly installed facilities of Specific Safety Facilities for Sendai Nuclear Power Station Unit No.2
09-04-2019 (Information)Submission for the notification of change in Electricity Generation Business regarding decommissioning of Genkai nuclear power station No.2
03-04-2019 (Information)Permission for a change in reactor installation of Specific Safety Facilities regarding efforts to improve safety and reliability of Genkai Nuclear Power Station No.3,4